Program 2020 Q & A
Q. What is Program 2020?
Power Point Dec 2015
A. Program 2020 is a 5-year plan presented to the Board of Directors in Oct 2015. It was provided by the Facilities Development Committee and the Finance Committee, and was a plan to incrementally increase dues to accommodate the repair & replacement of many of the most urgent facilities in our community, to be completed by 2020.
The East Lake Pool was added into the plan in Nov 2015, when the pool unexpectedly failed inspection and was decommissioned.
The Association was sued immediately following the Board approval of Program 2020.
Q. Where are we now?
A. The Pavilion has been built, the East Lake Pool is under construction, East Lake Marina has been renovated.
The Activities Center will unfortunately be postponed indefinitely due to the lawsuit and pending results of the subsequent vote of membership, to be held on Nov 6-15, 2017.
Power Point Dec 2015
A. Program 2020 is a 5-year plan presented to the Board of Directors in Oct 2015. It was provided by the Facilities Development Committee and the Finance Committee, and was a plan to incrementally increase dues to accommodate the repair & replacement of many of the most urgent facilities in our community, to be completed by 2020.
The East Lake Pool was added into the plan in Nov 2015, when the pool unexpectedly failed inspection and was decommissioned.
The Association was sued immediately following the Board approval of Program 2020.
Q. Where are we now?
A. The Pavilion has been built, the East Lake Pool is under construction, East Lake Marina has been renovated.
The Activities Center will unfortunately be postponed indefinitely due to the lawsuit and pending results of the subsequent vote of membership, to be held on Nov 6-15, 2017.